Summer 2011
Welding Lab Upgrades
Remove existing smokeeaters, exhaust fans & duct work Gives additional Headroom, current headroom limits access with forklift and taller items
Clean & Paint the lab
New fume extractors/Collectors
Collection distance from welding surface: 15" - Preferred
"Low Vac System" Centralized system Installation of fume extractors New Duct Work for Extractors and Other Exhausts New welding booths Reorganizes shop layout for more useable floor/work space
Relocate & add electrical power for WeldersRelocate & add electrical power for Fume Extractor Relocate & add air lines (Depending on New Fume Extractor needs) Rework Metal Former to 460v or 120v Rework Mechanical - HV, Dampers, Controls, VFD WBRC Design - Design Electrical/HV Summit Enviromental - Cleaning Work Plan Similar Unit:
100_3924.JPG 100_3925.JPG 100_3926.JPG 100_3927.JPG 100_3928.JPG 100_3929.JPG 100_3930.JPG 100_3931.JPG 100_3932.JPG 100_3933.JPG 100_3934.JPG 100_3935.JPG 100_3936.JPG 100_3953.JPG 100_3954.JPG 100_3955.JPG 100_3956.JPG 100_3957.JPG 100_3958.JPG 100_3959.JPG 100_3960.JPG 100_3961.JPG 100_3962.JPG 100_3963.JPG 100_3964.JPG 100_3965.JPG 100_3966.JPG 100_3967.JPG 100_3968.JPG 100_3969.JPG 100_3970.JPG 100_3971.JPG 100_3977.JPG 100_3978.JPG 100_3979.JPG 100_3980.JPG 100_3981.JPG 100_3982.JPG 100_3983.JPG 100_4080.JPG 100_4386.JPG 100_4387.JPG 100_4388.JPG 100_4389.JPG 100_4390.JPG 100_4391.JPG 100_4392.JPG 100_4393.JPG 100_4394.JPG 100_4395.JPG 100_4396.JPG 100_4397.JPG 100_4398.JPG 100_4399.JPG 100_4400.JPG 100_4401.JPG 100_4403.JPG 100_4404.JPG 100_4405.JPG 100_4406.JPG 100_4408.JPG 100_4409.JPG 100_4410.JPG 100_4411.JPG 100_4412.JPG 100_4417.JPG 100_4418.JPG 100_4419.JPG 100_4504.JPG 100_4505.JPG 100_4506.JPG 100_4510.JPG 100_4514.JPG 100_4518.JPG 100_4519.JPG 100_4520.JPG 100_4521.JPG 100_4536.JPG 100_4537.JPG 100_4538.JPG 100_4539.JPG 100_4540.JPG 100_4541.JPG 100_4562.JPG 100_4563.JPG 100_4564.JPG 100_4565.JPG 100_4566.JPG 100_4622.JPG 100_4623.JPG |