Summer 2011
Welding Lab Upgrades
Remove existing smokeeaters, exhaust fans & duct work Gives additional Headroom, current headroom limits access with forklift and taller items
Clean & Paint the lab
New fume extractors/Collectors
Collection distance from welding surface: 15" - Preferred
"Low Vac System" Centralized system Installation of fume extractors New Duct Work for Extractors and Other Exhausts New welding booths Reorganizes shop layout for more useable floor/work space
Relocate & add electrical power for WeldersRelocate & add electrical power for Fume Extractor Relocate & add air lines (Depending on New Fume Extractor needs) Rework Metal Former to 460v or 120v Rework Mechanical - HV, Dampers, Controls, VFD WBRC Design - Design Electrical/HV Summit Enviromental - Cleaning Work Plan Similar Unit:
100_5253.JPG 100_5254.JPG 100_5255.JPG 100_5256.JPG 100_5263.JPG 100_5264.JPG 100_5265.JPG 100_5266.JPG 100_5267.JPG 100_5268.JPG 100_5269.JPG 100_5270.JPG 100_5271.JPG 100_5272.JPG 100_5273.JPG 100_5274.JPG 100_5320.JPG 100_5321.JPG 100_5322.JPG 100_5323.JPG 100_5324.JPG 100_5325.JPG 100_5326.JPG 100_5327.JPG 100_5328.JPG 100_5329.JPG 100_5330.JPG 100_5331.JPG 100_5339.JPG 100_5340.JPG 100_5342.JPG 100_5343.JPG 100_5346.JPG 100_5347.JPG 100_5348.JPG 100_5349.JPG 100_5350.JPG 100_5351.JPG 100_5352.JPG 100_5353.JPG 100_5366.JPG 100_5367.JPG 100_5369.JPG 100_5370.JPG 100_5372.JPG 100_5373.JPG 100_5374.JPG 100_5375.JPG 100_5376.JPG 100_5378.JPG 100_5379.JPG 100_5380.JPG 100_5381.JPG 100_5382.JPG 100_5383.JPG 100_5399.JPG 100_5400.JPG 100_5401.JPG 100_5409.JPG 100_5410.JPG 100_5411.JPG 100_5412.JPG 100_5413.JPG 100_5416.JPG 100_5417.JPG 100_5418.JPG 100_5419.JPG 100_5427.JPG 100_5428.JPG 100_5429.JPG 100_5547.JPG 100_5548.JPG 100_5549.JPG 100_5550.JPG 100_5551.JPG 100_5552.JPG 100_5553.JPG 100_5554.JPG 100_5592.JPG 100_5593.JPG 100_5594.JPG 100_5595.JPG 100_5596.JPG 100_5597.JPG 100_5598.JPG 100_5599.JPG 100_5600.JPG 100_5601.JPG 100_5602.JPG 100_5603.JPG |