Summer 2011
Welding Lab Upgrades
Remove existing smokeeaters, exhaust fans & duct work Gives additional Headroom, current headroom limits access with forklift and taller items
Clean & Paint the lab
New fume extractors/Collectors
Collection distance from welding surface: 15" - Preferred
"Low Vac System" Centralized system Installation of fume extractors New Duct Work for Extractors and Other Exhausts New welding booths Reorganizes shop layout for more useable floor/work space
Relocate & add electrical power for WeldersRelocate & add electrical power for Fume Extractor Relocate & add air lines (Depending on New Fume Extractor needs) Rework Metal Former to 460v or 120v Rework Mechanical - HV, Dampers, Controls, VFD WBRC Design - Design Electrical/HV Summit Enviromental - Cleaning Work Plan Similar Unit:
100_5017.JPG 100_5018.JPG 100_5032.JPG 100_5033.JPG 100_5034.JPG 100_5035.JPG 100_5036.JPG 100_5037.JPG 100_5038.JPG 100_5039.JPG 100_5040.JPG 100_5041.JPG 100_5042.JPG 100_5043.JPG 100_5044.JPG 100_5045.JPG 100_5093.JPG 100_5094.JPG 100_5095.JPG 100_5096.JPG 100_5097.JPG 100_5098.JPG 100_5116.JPG 100_5117.JPG 100_5118.JPG 100_5119.JPG 100_5120.JPG 100_5136.JPG 100_5137.JPG 100_5138.JPG 100_5139.JPG 100_5140.JPG 100_5142.JPG 100_5143.JPG 100_5144.JPG 100_5145.JPG 100_5146.JPG 100_5150.JPG 100_5151.JPG 100_5152.JPG 100_5174.JPG 100_5175.JPG 100_5176.JPG 100_5177.JPG 100_5178.JPG 100_5179.JPG 100_5180.JPG 100_5181.JPG 100_5182.JPG 100_5183.JPG 100_5184.JPG 100_5185.JPG 100_5186.JPG 100_5187.JPG 100_5188.JPG 100_5189.JPG 100_5199.JPG 100_5200.JPG 100_5201.JPG 100_5202.JPG 100_5203.JPG 100_5204.JPG 100_5205.JPG 100_5206.JPG 100_5207.JPG 100_5208.JPG 100_5209.JPG 100_5210.JPG 100_5211.JPG 100_5212.JPG 100_5213.JPG 100_5214.JPG 100_5215.JPG 100_5217.JPG 100_5218.JPG 100_5219.JPG 100_5220.JPG 100_5221.JPG 100_5222.JPG 100_5223.JPG 100_5224.JPG 100_5244.JPG 100_5245.JPG 100_5246.JPG 100_5247.JPG 100_5248.JPG 100_5249.JPG 100_5250.JPG 100_5251.JPG 100_5252.JPG |