Summer 2011
Welding Lab Upgrades
Remove existing smokeeaters, exhaust fans & duct work Gives additional Headroom, current headroom limits access with forklift and taller items
Clean & Paint the lab
New fume extractors/Collectors
Collection distance from welding surface: 15" - Preferred
"Low Vac System" Centralized system Installation of fume extractors New Duct Work for Extractors and Other Exhausts New welding booths Reorganizes shop layout for more useable floor/work space
Relocate & add electrical power for WeldersRelocate & add electrical power for Fume Extractor Relocate & add air lines (Depending on New Fume Extractor needs) Rework Metal Former to 460v or 120v Rework Mechanical - HV, Dampers, Controls, VFD WBRC Design - Design Electrical/HV Summit Enviromental - Cleaning Work Plan Similar Unit:
100_4624.JPG 100_4625.JPG 100_4626.JPG 100_4627.JPG 100_4628.JPG 100_4630.JPG 100_4631.JPG 100_4657.JPG 100_4658.JPG 100_4659.JPG 100_4660.JPG 100_4661.JPG 100_4662.JPG 100_4663.JPG 100_4664.JPG 100_4665.JPG 100_4677.JPG 100_4678.JPG 100_4679.JPG 100_4680.JPG 100_4681.JPG 100_4682.JPG 100_4683.JPG 100_4684.JPG 100_4725.JPG 100_4747.JPG 100_4748.JPG 100_4749.JPG 100_4750.JPG 100_4751.JPG 100_4752.JPG 100_4753.JPG 100_4754.JPG 100_4755.JPG 100_4756.JPG 100_4757.JPG 100_4758.JPG 100_4759.JPG 100_4760.JPG 100_4761.JPG 100_4762.JPG 100_4763.JPG 100_4764.JPG 100_4765.JPG 100_4766.JPG 100_4767.JPG 100_4768.JPG 100_4772.JPG 100_4773.JPG 100_4774.JPG 100_4775.JPG 100_4776.JPG 100_4777.JPG 100_4778.JPG 100_4779.JPG 100_4809.JPG 100_4810.JPG 100_4811.JPG 100_4812.JPG 100_4832.JPG 100_4833.JPG 100_4834.JPG 100_4835.JPG 100_4836.JPG 100_4837.JPG 100_4838.JPG 100_4839.JPG 100_4840.JPG 100_4841.JPG 100_4842.JPG 100_4843.JPG 100_4879.JPG 100_4880.JPG 100_4881.JPG 100_4882.JPG 100_4883.JPG 100_4898.JPG 100_4899.JPG 100_4900.JPG 100_5006.JPG 100_5007.JPG 100_5008.JPG 100_5009.JPG 100_5010.JPG 100_5011.JPG 100_5012.JPG 100_5013.JPG 100_5014.JPG 100_5015.JPG 100_5016.JPG |